Dining room
2 missing 7/8th nuts and tighten down
Corner
SR backing at corner beam
SR backing above door at header
Add missing block
(10’+ spans need blocks)
Add strap at top plate
Add blocks at left corner
Nail sheer pattern in ply outside
Add strap at top plate
Add missing stud.
Tighten new glued HD
Kitchen
Strap sheer wall to double top plate
Fur out studs at sheer panel right
Nail off sheer panel to top plate
Check nailing on sheer wall
Great room
A35 x 3 to beam area
Fix A35 at door opening
Strap large Glulam to LVL
Check for missing hardware for big window rake wall.
A35s
Strap left
Strap right
Tighten corner holddowns
Nail off king stud top
Check plate breaks
Rear portch
Remove braces
Shave off bolts too deep counter sink
Flush facia with 3 blue screws
Entry
5 A35s and 5 H1s at outlookers
Strap wall at beam w no top plate
Shave bolts x8
Sheer beam
Closet
Strap wall to header front
Master bath
7/8th but on hold down
Corner backing
Master bedroom
7/8th but on hold down
Strap header x3 (one extra long one 3-4’)
Strap corner at short wall
Corner backing
Stairs
Fill in 3 knee wall areas
Add toe kickers x2
Block upper area/sheet
Ledger to back
Fur strip wall area
Upstairs
Fur up headers x 3
Fur corner at sheer wall
Add backer at peak